  1. 16 September 2021Arbitration

    2 years, 9 months and 9 days later · 1013 days

  2. 25 June 2024France

    25 June 2024France

    Order Revoking the Closing Order of the Paris Court of Appeal in case RG 23/09587 dated 25 June 2024

    Paris Court of Appeal, Division 5 - Chamber 16

    Case no.
    RG 23/09587
    Decision summary
    The Paris Court of Appeal revoked the closing order issued on 11 June 2024 because a serious cause justified reopening the proceedings, and remanded the case to the case-management hearing of 8 October 2024 at 13:00.

    Supporting details

    1 authority · 9 participants
    Monsieur [B] [Y]
    Representative
    Jean-Claude CHEVILLER (For: Monsieur [B] [Y] · Monsieur [F] [O] · Monsieur [L] [Z])
    Monsieur [F] [O]
    Representative
    Jean-Claude CHEVILLER (For: Monsieur [B] [Y] · Monsieur [F] [O] · Monsieur [L] [Z])
    Monsieur [L] [Z]
    Representative
    Jean-Claude CHEVILLER (For: Monsieur [B] [Y] · Monsieur [F] [O] · Monsieur [L] [Z])
    Société China Communications Construction Company Ltd
    Representative
    Luca DE MARIA (For: Société China Communications Construction Company Ltd)
    Representative
    SELARL PELLERIN - DE MARIA - GUERRE (For: Société China Communications Construction Company Ltd)
    Paris Court of Appeal, Division 5 - Chamber 16
    Other
    Institutional administrator
    Najma EL FARISSI

    Authorities cited

    1
    • French Code of Civil Procedure (Article 784 of the French Code of Civil Procedure)
      statute