Total S.A. v. Argentine Republic (ICSID Case No. ARB/04/1)
- 25 August 2006Arbitration
25 August 2006Arbitration
Decision on Objections to Jurisdiction dated 25 August 2006
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal rejected Argentina's objections to jurisdiction and held that the dispute fell within ICSID jurisdiction and the Tribunal's competence, reserving the costs of the jurisdictional phase for the merits phase.
Supporting details
4 authorities · 6 participantsTotal S.A.
The Argentine Republic
International Centre for Settlement of Investment Disputes
- Arbitrator
- Giorgio Sacerdoti
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Luis Herrera Marcano
- Tribunal secretary
- Gabriela Alvarez Avila
4 years, 4 months and 2 days later · 1585 days
- 27 December 2010Arbitration
27 December 2010Arbitration
Decision on Liability dated 27 December 2010
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal partially granted Total's claims, found that Argentina breached Article 3 of the Argentina-France BIT by failing to provide fair and equitable treatment, rejected the other claims and Argentina's defences, held Argentina liable for the resulting damage, and reserved quantification and costs for a later phase.
Supporting details
7 authorities · 7 participantsTotal S.A.
The Argentine Republic
International Centre for Settlement of Investment Disputes
- Arbitrator
- Giorgio Sacerdoti
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Luis Herrera Marcano
- Tribunal secretary
- Natali Sequeira
- Tribunal secretary
- Eloise Obadia
2 years and 11 months later · 1066 days
- 27 November 2013Arbitration
27 November 2013Arbitration
Award dated 27 November 2013
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal ordered Argentina to pay Total compensation for damage caused by breaches of Article 3 of the Argentina-France BIT, including US$269,928,000 before interest. It ordered interest, allocated legal costs separately, and required the parties to share the Tribunal and ICSID costs equally; all other claims, defences and exceptions were rejected.
Supporting details
5 authorities · 6 participantsTotal S.A.
The Argentine Republic
International Centre for Settlement of Investment Disputes
- Arbitrator
- Giorgio Sacerdoti
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Luis Herrera Marcano
- Tribunal secretary
- Natali Sequeira
1 year, 8 months and 30 days later · 637 days
- 26 August 2015Arbitration
26 August 2015Arbitration
Decision on the Argentine Republic's Proposal to Disqualify Ms. Teresa Cheng dated 26 August 2015
International Centre for Settlement of Investment Disputes
- Decision summary
- The majority of the ad hoc Committee rejected the Argentine Republic's proposal to disqualify Teresa Cheng, lifted the stay of the annulment proceedings, and reserved costs for a later stage.
Supporting details
2 authorities · 6 participantsTotal S.A.
Argentine Republic
Eduardo Zuleta Jaramillo
International Centre for Settlement of Investment Disputes
- Arbitrator
- Alvaro Castellanos Howell
- Arbitrator
- Teresa Cheng
- Tribunal secretary
- Giuliana Cane
5 months and 6 days later · 159 days
- 1 February 2016Arbitration
1 February 2016Arbitration
Decision on Annulment dated 1 February 2016
International Centre for Settlement of Investment Disputes
- Decision summary
- The ad hoc Committee unanimously dismissed Argentina's application for annulment of the Award. Each party was ordered to bear its own legal costs and expenses, and Argentina was ordered to bear the costs of the annulment proceeding, including the Committee members' fees and expenses and the costs of using ICSID facilities.
Supporting details
5 authorities · 6 participantsTotal S.A.
Argentine Republic
Eduardo Zuleta Jaramillo
International Centre for Settlement of Investment Disputes
- Arbitrator
- Teresa Cheng
- Arbitrator
- Alvaro Castellanos Howell
- Tribunal secretary
- Giuliana Cane