Mabco Constructions SA v. Republic of Kosovo (ICSID Case No. ARB/17/25)
- 5 October 2018France
5 October 2018France
Procedural Order No. 1
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal set the procedural rules for the arbitration, confirmed its constitution, fixed Paris, France as the place of proceeding, and set procedures for the conduct of the case.
Supporting details
4 authorities · 2 participantsMabco Constructions SA
Republic of Kosovo
International Centre for Settlement of Investment Disputes
8 months and 16 days later · 259 days
- 21 June 2019France
21 June 2019France
Procedural Order No. 2
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal resolved the parties' disagreements concerning document production and attached the completed Redfern Schedules as annexes.
Supporting details
International Centre for Settlement of Investment Disputes
3 months and 19 days later · 111 days
- 10 October 2019France
10 October 2019France
Procedural Order No. 3
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal set the specifications for the hearing on jurisdiction and admissibility, including the hearing schedule, witness examination, hearing materials, and cost submissions.
Supporting details
International Centre for Settlement of Investment Disputes
1 year and 20 days later · 386 days
- 30 October 2020France
30 October 2020France
Decision on Jurisdiction
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal upheld the Respondent's ratione temporis objections to the expropriation and fair and equitable treatment claims under the BIT, but rejected the objection to the denial of justice claim. It rejected the ratione temporis objections under the Foreign Investment Law, rejected by majority the ratione materiae and ratione personae objections, rejected the other jurisdictional objections, and deferred allocation of costs.
Supporting details
11 authorities · 6 participantsMabco Constructions SA
Republic of Kosovo
International Centre for Settlement of Investment Disputes
Other
- Witness
- Behgjet Pacolli
- Witness
- Remzi Ejupi
- Witness
- Lucina Maesani-Gaiatto
- Witness
- Ahmet Shala
1 year, 1 month and 1 day later · 397 days
- 1 December 2021France
1 December 2021France
Procedural Order No. 4
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal recorded its decisions on the parties' Redfern Schedules in the final columns of the attached schedules.
Supporting details
International Centre for Settlement of Investment Disputes
12 days later · 12 days
- 13 December 2021France
13 December 2021France
Procedural Order No. 5
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal granted the Respondent's amended request for production concerning correspondence about the Grand Hotel privatization.
Supporting details
International Centre for Settlement of Investment Disputes
7 days later · 7 days
- 20 December 2021France
20 December 2021France
Procedural Order No. 6
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal found the Claimant's narrowed production request not untimely, invited the Claimant to define the documents sought with greater specificity, and allowed a revised request.
Supporting details
International Centre for Settlement of Investment Disputes
3 months and 30 days later · 120 days
- 19 April 2022France
19 April 2022France
Procedural Order No. 7
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal granted the request to exclude Ferial El Ayeb's expert opinion, denied the request to exclude Artan Qerkini's expert opinion, and extended the Respondent's deadline to respond.
Supporting details
International Centre for Settlement of Investment Disputes
1 month and 27 days later · 57 days
- 15 June 2022France
15 June 2022France
Procedural Order No. 8
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal resolved the Claimant's procedural requests concerning new witnesses, Qerim Qerimi's second report, allegedly defamatory exhibits, the UNMIK Police Report, the KTA and PAK relationship, translations, and costs. It allowed limited further submissions and reserved judgment on costs.
Supporting details
International Centre for Settlement of Investment Disputes
- 15 June 2022France
15 June 2022France
Procedural Order No. 9
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal organized the merits hearing, fixed the hearing dates and venue in Geneva, Switzerland, set the order of proceedings and time allocation, and identified hearing participants and logistical arrangements.
Supporting details
International Centre for Settlement of Investment Disputes
4 days later · 4 days
- 19 June 2022France
19 June 2022France
Procedural Order No. 10
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal found that the matters identified in the Second Qerimi Report were not new in the relevant sense, but allowed the Claimant to identify documents it would have introduced and stated that it would consider their admission for the hearings.
Supporting details
International Centre for Settlement of Investment Disputes
4 months and 1 day later · 123 days
- 20 October 2022France
20 October 2022France
Procedural Order No. 12
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal granted the Claimant an opportunity to comment on the Shkodra Documents, declined at that time to allow expert testimony on investigative procedure, and directed the parties to confer on a schedule.
Supporting details
International Centre for Settlement of Investment Disputes
2 months and 7 days later · 68 days
- 27 December 2022France
27 December 2022France
Procedural Order No. 13
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal ruled that the Claimant's receipt and submission of the November 27, 2012 Report and related exhibits did not breach Procedural Order No. 12, allowed the exhibits into evidence despite the failure to seek advance leave, and ordered the Claimant to replace Exhibit C-131 with an unmarked version.
Supporting details
International Centre for Settlement of Investment Disputes
5 months and 17 days later · 168 days
- 13 June 2023France
13 June 2023France
Procedural Order No. 14
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal granted the Claimant leave to comment on the Respondent's Addendum to its Post-Hearing Brief and set successive deadlines for comments and replies.
Supporting details
International Centre for Settlement of Investment Disputes