Arbitral Digest

Matter

Amec Foster Wheeler USA Corporation, Process Consultants, Inc., and Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc. v. Republic of Colombia (ICSID Case No. ARB/19/34)

Case no.
ARB/19/34
Applicable rules
ICSID Arbitration Rules in force as of April 2006
  1. 18 March 2021Arbitration

    18 March 2021Arbitration

    Procedural Order No. 1 dated March 18, 2021

    International Centre for Settlement of Investment Disputes

    Supporting details

    4 participants
    Amec Foster Wheeler USA Corporation
    Process Consultants, Inc.
    Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc.
    Republic of Colombia
    International Centre for Settlement of Investment Disputes

    7 months and 7 days later · 221 days

  2. 25 October 2021Arbitration

    25 October 2021Arbitration

    Tribunal Decision on Claimants' Request for Emergency Temporary Relief dated October 25, 2021

    International Centre for Settlement of Investment Disputes

    Supporting details

    4 participants
    Amec Foster Wheeler USA Corporation
    Process Consultants, Inc.
    Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc.
    Republic of Colombia
    International Centre for Settlement of Investment Disputes

    6 months and 1 day later · 183 days

  3. 26 April 2022Arbitration

    26 April 2022Arbitration

    Procedural Order No. 2 dated April 26, 2022

    International Centre for Settlement of Investment Disputes

    Supporting details

    4 participants
    Amec Foster Wheeler USA Corporation
    Process Consultants, Inc.
    Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc.
    Republic of Colombia
    International Centre for Settlement of Investment Disputes

    1 month and 5 days later · 35 days

  4. 31 May 2022Arbitration

    31 May 2022Arbitration

    Procedural Order No. 3 - Decision on Claimants' Application for Provisional Measures dated May 31, 2022

    International Centre for Settlement of Investment Disputes

    Supporting details

    4 participants
    Amec Foster Wheeler USA Corporation
    Process Consultants, Inc.
    Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc.
    Republic of Colombia
    International Centre for Settlement of Investment Disputes

    2 years, 6 months and 18 days later · 933 days

  5. 19 December 2024Arbitration

    19 December 2024Arbitration

    Award dated December 19, 2024

    International Centre for Settlement of Investment Disputes

    Supporting details

    4 participants
    Amec Foster Wheeler USA Corporation
    Process Consultants, Inc.
    Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc.
    Republic of Colombia
    International Centre for Settlement of Investment Disputes

    9 months and 5 days later · 279 days

  6. 24 September 2025Arbitration

    24 September 2025Arbitration

    Procedural Order No. 1 dated September 24, 2025

    International Centre for Settlement of Investment Disputes

    Supporting details

    4 participants
    Amec Foster Wheeler USA Corporation
    Process Consultants, Inc.
    Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc.
    Republic of Colombia
    International Centre for Settlement of Investment Disputes

Matter record

Report a correction

Amec Foster Wheeler USA Corporation, Process Consultants, Inc., and Joint Venture Foster Wheeler USA Corporation and Process Consultants, Inc. v. Republic of Colombia (ICSID Case No. ARB/19/34) · Matter