  1. 20 December 2023Arbitration

    20 December 2023Arbitration

    Procedural Order No. 1

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal established the procedural rules and procedural calendar governing the arbitration.

    Supporting details

    International Centre for Settlement of Investment Disputes

    1 month and 6 days later · 37 days

  2. 26 January 2024Arbitration

    26 January 2024Arbitration

    Procedural Order No. 2

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal ordered publication of procedural orders, decisions on jurisdiction or liability, and the award; ordered publication of party position summaries; and denied publication of pleadings, expert opinions, witness statements, and hearing transcripts.

    Supporting details

    International Centre for Settlement of Investment Disputes

    8 months and 14 days later · 258 days

  3. 10 October 2024Arbitration

    10 October 2024Arbitration

    Procedural Order No. 3

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal recognized the La Gran Parada and Paradero Communities as non-disputing parties, permitted a limited written submission and supporting documents, denied participation in hearings, and reserved costs.

    Supporting details

    3 participants
    La Gran Parada Community
    Paradero Community
    Colectivo de Abogados y Abogadas Jose Alvear Restrepo
    International Centre for Settlement of Investment Disputes

    6 months and 13 days later · 195 days

  4. 23 April 2025Arbitration

    23 April 2025Arbitration

    Procedural Order No. 4

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal directed the Communities to file a revised non-disputing-party submission, exclude specified exhibits, redact individual signatories before publication, and denied all other requests.

    Supporting details

    International Centre for Settlement of Investment Disputes

    1 month and 5 days later · 35 days

  5. 28 May 2025Arbitration

    28 May 2025Arbitration

    Procedural Order No. 5

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal ordered publication of the revised non-disputing-party submission subject to redaction of individual signatories, confirmed the revised procedural calendar, and reserved costs.

    Supporting details

    International Centre for Settlement of Investment Disputes

    2 months and 3 days later · 64 days

  6. 31 July 2025Arbitration

    31 July 2025Arbitration

    Procedural Order No. 6

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal denied the Claimant's application to exclude material relating to the Rejoinder Mine Plans, invited responsive submissions and evidence by 13 October 2025, and reserved costs.

    Supporting details

    International Centre for Settlement of Investment Disputes

    2 months and 6 days later · 68 days

  7. 7 October 2025Arbitration

    7 October 2025Arbitration

    Procedural Order No. 8

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal denied the Respondent's application to strike Exhibit C-370 and reserved costs.

    Supporting details

    International Centre for Settlement of Investment Disputes

    22 days later · 22 days

  8. 29 October 2025Arbitration

    29 October 2025Arbitration

    Procedural Order No. 7 - Hearing Organization

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal set the organization, format, schedule, examination procedure, and logistical arrangements for the hearing.

    Supporting details

    International Centre for Settlement of Investment Disputes

    2 months and 28 days later · 89 days

  9. 26 January 2026Arbitration

    26 January 2026Arbitration

    Procedural Order No. 9 - Annex A

    International Centre for Settlement of Investment Disputes

    Supporting details

    International Centre for Settlement of Investment Disputes
  10. 26 January 2026Arbitration

    26 January 2026Arbitration

    Procedural Order No. 9 - Post-Hearing Matters

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal directed the preparation and filing of post-hearing briefs, set procedures for additional evidence and legal authorities, addressed possible supplemental expert evidence and cost statements, and issued a revised procedural calendar.

    Supporting details

    International Centre for Settlement of Investment Disputes

    2 months and 5 days later · 64 days

  11. 31 March 2026Arbitration

    31 March 2026Arbitration

    Procedural Order No. 10

    International Centre for Settlement of Investment Disputes

    Decision summary
    The Tribunal granted leave for the Respondent to introduce four new documentary exhibits and two awards, granted leave for the Claimant to introduce thirteen legal authorities, admitted a supplemented authority, and directed the Parties to submit the admitted materials within three days.

    Supporting details

    International Centre for Settlement of Investment Disputes

Matter record

Report a correction

Glencore International A.G. v. Republic of Colombia (ICSID Case No. ARB/21/30) · Matter