Matter
Fotowatio Renewable Ventures S.L.U., FRV Solar Holdings III, S.L.U. and FRV Solar Holdings VI, S.L.U. v. United Mexican States (ICSID Case No. ARB/24/5)
- 11 September 2024Arbitration
11 September 2024Arbitration
Procedural Order No. 1
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal set the procedural rules and timetable for the arbitration, confirmed the constitution of the Tribunal, designated Washington, D.C. as the place of the proceeding, and addressed representation, document production, hearings, and related procedural matters.
Supporting details
8 participantsFotowatio Renewable Ventures S.L.U.
FRV Solar Holdings III, S.L.U.
FRV Solar Holdings VI, S.L.U.
United Mexican States
International Centre for Settlement of Investment Disputes
- Arbitrator
- Sir Christopher Greenwood
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Monica Pinto
- Tribunal secretary
- Gabriela Gonzalez Giraldez
- 11 September 2024Arbitration
11 September 2024Arbitration
Procedural Order No. 2 on Transparency and Confidentiality
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal adopted the transparency and confidentiality regime governing the proceeding, including procedures for publication and redaction of the Award, orders, decisions, and other case materials.
Supporting details
8 participantsFotowatio Renewable Ventures S.L.U.
FRV Solar Holdings III, S.L.U.
FRV Solar Holdings VI, S.L.U.
United Mexican States
International Centre for Settlement of Investment Disputes
- Arbitrator
- Sir Christopher Greenwood
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Monica Pinto
- Tribunal secretary
- Gabriela Gonzalez Giraldez
7 months and 3 days later · 215 days
- 14 April 2025Arbitration
14 April 2025Arbitration
Procedural Order No. 3: Decision on Bifurcation
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal rejected the Respondent's request to bifurcate the jurisdictional objections, ended the suspension of the proceeding with immediate effect, directed the proceeding to resume under the amended timetable, and reserved the costs of the bifurcation request for the Award.
Supporting details
7 authorities · 8 participantsFotowatio Renewable Ventures S.L.U.
FRV Solar Holdings III, S.L.U.
FRV Solar Holdings VI, S.L.U.
United Mexican States
International Centre for Settlement of Investment Disputes
- Arbitrator
- Sir Christopher Greenwood
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Monica Pinto
- Tribunal secretary
- Gabriela Gonzalez Giraldez
6 months and 7 days later · 190 days
- 21 October 2025Arbitration
21 October 2025Arbitration
Procedural Order No. 4: Decision on Document Production
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal ruled on the Parties' requests and objections concerning document production. It directed the Respondent to produce the documents identified in Schedule A and the Claimants to produce the documents identified in Schedule B by 4 November 2025, subject to provisions on privilege, confidentiality, and political or institutional sensitivity.
Supporting details
8 participantsFotowatio Renewable Ventures S.L.U.
FRV Solar Holdings III, S.L.U.
FRV Solar Holdings VI, S.L.U.
United Mexican States
International Centre for Settlement of Investment Disputes
- Arbitrator
- Sir Christopher Greenwood
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Monica Pinto
- Tribunal secretary
- Gabriela Gonzalez Giraldez
2 months and 2 days later · 63 days
- 23 December 2025Arbitration
23 December 2025Arbitration
Procedural Order No. 5: Decision on Privilege Claims
International Centre for Settlement of Investment Disputes
- Decision summary
- The Tribunal decided the Respondent's claims of political and institutional sensitivity and confidentiality of third-party information in Schedule A and the Claimants' privilege claims in Schedule B. It directed the Respondent and the Claimants to complete the production and review steps specified in the Order by 9 January 2026.
Supporting details
8 participantsFotowatio Renewable Ventures S.L.U.
FRV Solar Holdings III, S.L.U.
FRV Solar Holdings VI, S.L.U.
United Mexican States
International Centre for Settlement of Investment Disputes
- Arbitrator
- Sir Christopher Greenwood
- Arbitrator
- Henri C. Alvarez
- Arbitrator
- Monica Pinto
- Tribunal secretary
- Gabriela Gonzalez Giraldez